Warehouse Lighting

DPSS have recently completed the installation of 72 High Bay lights and new Distribution Board at a brand new Warehouse in Heathrow, London.

All cables, CMS, Bracketry & Lights were installed on time and within budget for the client., glanding, terminating & testing completed too.

Our lead Level 4 Electrician,  City & Guilds 2396 Design & Verification qualified & BTEC Level 4 HNC Diploma in Construction and the Built Environment,  desiged the contactors layouts and lighting circuits for the client. A new DB was also installed to support the lighting circuits.

The guys at DPSS have enjoyed working on a different project during the COVID-19 Pandemic. To ensure their safety they have their temperature taken before starting on site and wear masks to protect themselves and others.

 

4

5

3

2

1

6

DPSS have been busy….

DPSS have been very busy in the office putting tenders and prices together for future works, some of the works we have been doing out on site are as follows:

  • SWIP Tranche 2 Installs at various sites across London Underground
  • Walthamstow Central CCTV upgrade works
  • Firstco Greenwich Power Station installation works
  • Cubic SC3 Ticket machine upgrade works
  • Fit for the Future ticket hall works

 

This is the installation works we have been completing for Tranche 2 at Latimer Road…

2015-08-18 23.37.34

2015-08-18 23.38.35

Project Focus – Next Train Indicators

Project Title: Next Train Indicators

Sites: Southfields, Wimbledon Park, Putney Bridge, West Brompton & Seven Sisters

Client: Station Works Improvement Program & TFL

Duration: November 2014 to May 2015

Description: DPSS surveyed all 5 sites and carried out Structural Assessments prior to producing a Conceptual Design Specification document for LUL Asset Engineers Approval. A Total of 7 NTIs were installed across 5 platforms and 2 Concourse Areas on Posts or Brackets. Power and Communication cables were run and associated CMS where required.

DPSS carried out “Trial Fits” of the units on Seven Sisters Platform 4 to ensue that the proposed location did not interfere with the Train Drivers OPO Camera Views.

All cables were terminated and tested and information provided to TFL to allow the NOWRI to be passed and to allow bringing into service.

IMG_6073 image2

image3 IMG_4873

IMG_4874