Next Train Indicators

Next Train Indicators

DPSS surveyed 5 sites and carried out Structural Assessments prior to producing a Conceptual Design Specification document for LUL Asset Engineers Approval. A Total of 7 NTIs were installed across 5 platforms and 2 Concourse Areas on Posts or Brackets. Power and Communication cables were run and associated CMS where required.
DPSS carried out “Trial Fits” of the units on Seven Sisters Platform 4 to ensue that the proposed location did not interfere with the Train Drivers OPO Camera Views.
All cables were terminated and tested and information provided to TFL to allow the NOWRI to be passed and to allow bringing into service.